Total Records: 184 Case #: PU-05-047
|
Docket # |
Description |
On Behalf Of |
Filed By |
Filed |
Pages |
| 184 |
Affidavit of Service by Certified Mail - Order |
Public Service Commission |
|
6/10/2021 |
3 |
| 183 |
Order |
Public Service Commission |
|
6/9/2021 |
2 |
| 182 |
Commission Motion to adopt Order |
Public Service Commission |
|
6/9/2021 |
1 |
| 181 |
Request of Rugby Wind for Extension of Light Mitigation Deadline |
Avangrid Renewables, LLC |
Jeffrey Durocher |
5/27/2021 |
3 |
| 180 |
Affidavit of Service by Regular Mail - Letter & Memorandum Originally Mailed May 10, 2021 |
Public Service Commission |
|
5/25/2021 |
4 |
| 179 |
Returned Mail - Affidavit of Service by Regular Mail |
United States Postal Service |
|
5/24/2021 |
1 |
| 178 |
Affidavit of Service by Regular Mail - Letter with Memorandum |
Public Service Commission |
|
5/10/2021 |
3 |
| 177 |
Letter with attached memorandum |
Public Service Commission |
Brian Johnson-Legal Counsel |
5/10/2021 |
3 |
| 176 |
Memorandum |
Public Service Commission |
Brian Johnson-Legal Counsel |
5/7/2021 |
1 |
| 175 |
Electronic recording of 20 Apr. 2021 Work Session |
Public Service Commission |
|
4/20/2021 |
1 |
| 174 |
Electronic recording of 14 Apr. 2021 Informal Hearing |
Public Service Commission |
|
4/14/2021 |
1 |
| 173 |
Petition for Extension of Light Mitigation Deadline |
Rugby Wind LLC |
Peter Landoni, Asset Manager |
3/22/2021 |
4 |
| 172 |
Letter enclosing final refund |
Public Service Commission |
|
6/5/2017 |
5 |
| 171 |
Commission Motion issuing siting application fee final refund |
Public Service Commission |
|
12/2/2015 |
1 |
| 170 |
No Archived File - Roll No. 603 |
Public Service Commission |
|
12/19/2013 |
1 |
| 169 |
Response to final construction report |
Rugby Wind LLC |
Peter Landoni |
10/15/2013 |
12 |
| 168 |
Letter request of compliance re post construction inspection recommended actions |
Public Service Commission Staff |
Jerry Lein |
8/15/2013 |
3 |
| 167 |
Year 3 of 3 tree replacement memo |
Iberdrola Renewables, Inc. |
Tina Bartunek |
10/1/2012 |
13 |
| 166 |
Tree monitoring memo |
Iberdrola Renewables, Inc. |
Tina Bartunek |
10/7/2011 |
14 |
| 165 |
Tree Survey Report |
Iberdrola Renewables, Inc. |
Sarah Emery |
12/27/2010 |
12 |
| 164 |
Invoice #12-0125 $353.16 |
Keitu Engineers & Consultants, Inc. |
|
2/1/2012 |
1 |
| 163 |
Invoice #12-0124 $2,016.27 |
Keitu Engineers & Consultants, Inc. |
|
2/1/2012 |
1 |
| 162 |
Final report for post-construction siting inspections |
Keitu Engineers & Consultants, Inc. |
Timothy Spilman |
1/27/2012 |
36 |
| 161 |
Invoice #11-01129 $177.26 |
Keitu Engineers & Consultants, Inc. |
|
12/12/2011 |
1 |
| 160 |
Invoice #11-0923 $2,104.90 |
Keitu Engineers & Consultants, Inc. |
|
9/16/2011 |
1 |
| 159 |
Invoice #11-0748 $221.58 |
Keitu Engineers & Consultants, Inc. |
|
8/15/2011 |
1 |
| 158 |
Fully executed contract for consulting services |
Keitu Engineers & Consultants, Inc. |
Timothy Spilman |
11/8/2010 |
9 |
| 157 |
Informal Hearing Audio |
Public Service Commission |
|
4/6/2011 |
1 |
| 156 |
Letter re Extraordinary event notification |
PPM Energy, Inc. |
Sarah Emery |
3/21/2011 |
1 |
| 155 |
Invoice #10-1130 $88.62 |
Keitu Engineers & Consultants, Inc. |
|
12/16/2010 |
1 |
| 154 |
Rugby Wind Farm As-Built maps |
Iberdrola Renewables, Inc. |
Keith Powers - Project Manager |
6/22/2010 |
45 |
| 153 |
Rugby Wind Weekly Status Update for week ending Dec. 19, 2009 |
Rugby Wind LLC |
|
12/21/2009 |
2 |
| 152 |
Rugby Wind Weekly Status Update for week ending Dec. 5, 2009 |
Rugby Wind LLC |
|
12/8/2009 |
2 |
| 151 |
Rugby Wind Weekly Status Update for week ending Nov. 21, 2009 |
Rugby Wind LLC |
|
11/23/2009 |
2 |
| 150 |
Rugby Wind Weekly Status Update for week ending Nov. 14, 2009 |
Rugby Wind LLC |
|
11/17/2009 |
2 |
| 149 |
Rugby Wind Weekly Status Update for week ending Nov. 7, 2009 |
Rugby Wind LLC |
|
11/9/2009 |
2 |
| 148 |
Rugby Wind Weekly Status Update for week ending Oct. 31, 2009 |
Rugby Wind LLC |
|
11/3/2009 |
2 |
| 147 |
Rugby Wind Weekly Status Update for week ending Oct. 24, 2009 |
Rugby Wind LLC |
|
10/26/2009 |
2 |
| 146 |
Rugby Wind Weekly Status Update, Oct. 17, 2009 |
Rugby Wind LLC |
|
10/19/2009 |
2 |
| 145 |
Rugby Wind Weekly Status Update, Oct. 10, 2009 |
Rugby Wind LLC |
|
10/12/2009 |
2 |
| 144 |
Rugby Wind Weekly Status Update, Oct. 3, 2009 |
Rugby Wind LLC |
|
10/5/2009 |
2 |
| 143 |
Rugby Wind Weekly Status Update, Sept. 26, 2009 |
Rugby Wind LLC |
|
9/28/2009 |
2 |
| 142 |
Rugby Wind Weekly Status Update, Sept. 19, 2009 |
Rugby Wind LLC |
|
9/21/2009 |
2 |
| 141 |
Rugby Wind Weekly Status Update, Sept. 12, 2009 |
Rugby Wind LLC |
|
9/14/2009 |
2 |
| 140 |
Rugby Wind Weekly Status Update, Sept. 5, 2009 |
Rugby Wind LLC |
|
9/8/2009 |
2 |
| 139 |
Rugby Wind Weekly Status Update, Aug. 29, 2009 |
Rugby Wind LLC |
|
8/29/2009 |
3 |
| 138 |
Rugby Wind Weekly Status Update, Aug. 22, 2009 |
Rugby Wind LLC |
|
8/24/2009 |
3 |
| 137 |
Rugby Wind Weekly Status Update, Aug. 15, 2009 |
Rugby Wind LLC |
|
8/18/2009 |
2 |
| 136 |
Rugby Wind Weekly Status Update, Aug. 8, 2009 |
Rugby Wind LLC |
|
8/10/2009 |
2 |
| 135 |
Rugby Wind Weekly Status Update, for week ending 8-1-09 |
Rugby Wind LLC |
|
8/3/2009 |
2 |
| 134 |
Rugby Wind Weekly Status Update, July 25, 2009 |
Rugby Wind LLC |
|
7/27/2009 |
3 |
| 133 |
Rugby Wind Weekly Status Update, July 18, 2009 |
Rugby Wind LLC |
|
7/21/2009 |
2 |
| 132 |
Rugby Wind Weekly Status Update, July 10, 2009 |
Rugby Wind LLC |
|
7/13/2009 |
2 |
| 131 |
Rugby Wind Weekly Status Update, July 3, 2009 |
Rugby Wind LLC |
|
7/6/2009 |
2 |
| 130 |
Rugby Wind Weekly Status Update, June 27, 2009 |
Rugby Wind LLC |
|
6/29/2009 |
2 |
| 129 |
Rugby Wind Weekly Status Update, June 20, 2009 |
Rugby Wind LLC |
|
6/22/2009 |
2 |
| 128 |
Rugby Wind Weekly Status Update, June 13, 2009 |
Rugby Wind LLC |
|
6/15/2009 |
2 |
| 127 |
Rugby Wind Weekly Status Update, June 6, 2009 |
Rugby Wind LLC |
|
6/8/2009 |
2 |
| 126 |
Rugby Wind Weekly Status Update, May 30, 2009 |
Rugby Wind LLC |
|
6/1/2009 |
2 |
| 125 |
Rugby Wind Weekly Status Update, May 23, 2009 |
Rugby Wind LLC |
|
5/26/2009 |
2 |
| 124 |
Letter Enclosing Commission Motion Acknowledging Staff Approval of Turbine Location Change |
Public Service Commission |
|
6/9/2009 |
2 |
| 123 |
Commission Motion Acknowledging Approval by Commission Staff of Proposed Turbine Location Change Request |
Public Service Commission |
|
6/3/2009 |
1 |
| 122 |
Staff Approval of Proposed Relocation Turbine J-1 with Map |
Public Service Commission Staff |
Jerry Lein |
5/22/2009 |
3 |
| 121 |
Letter – Rvw – of Class III CRI Rpt. & Concurrence with No Historic Properties Affected |
State Historical Society of North Dakota |
Merlan Paaverud, Director |
4/22/2009 |
1 |
| 120 |
Letter & Commission Motion Acknowledging Staff Approval of Turbine Structure Location Changes |
Public Service Commission |
|
1/26/2009 |
2 |
| 119 |
Staff Approval of Changes to Turbine Structure Locations |
Public Service Commission |
|
1/14/2009 |
4 |
| 118 |
Motion Acknowledging Approval of Turbine Structure Location Changes |
Public Service Commission |
|
1/14/2009 |
1 |
| 117 |
Rugby Wind LLC Weekly Project Information, Week Ending Dec. 6, 2008 |
Rugby Wind LLC |
Dennis Kuhns, Iberdrola Renewables |
12/6/2008 |
5 |
| 116 |
Affidavit Certified - First Reissued Site Certificate No. 5 |
Public Service Commission |
|
12/4/2008 |
3 |
| 115 |
Turbine Relocation Update |
Rugby Wind LLC |
|
12/4/2008 |
1 |
| 114 |
Turbine Relocation Update |
Rugby Wind LLC |
|
12/3/2008 |
2 |
| 113 |
Turbine Relocations Request |
Rugby Wind LLC |
Dennis E. Kuhns, Acting Site Manager |
12/2/2008 |
6 |
| 112 |
Motion Issuing Corrected First Reissued Certificate of Site Compatibility No. 5 |
Public Service Commission |
|
12/3/2008 |
2 |
| 111 |
Rugby Wind LLC Weekly Project Information, Week Ending Nov. 30, 2008 |
Rugby Wind LLC |
Dennis Kuhns, Iberdrola Renewables |
11/25/2008 |
2 |
| 110 |
Rugby Wind LLC Weekly Project Information, Week Ending Nov. 23, 2008 |
Rugby Wind LLC |
Dennis Kuhns, Iberdrola Renewables |
11/23/2008 |
2 |
| 109 |
Notice that Turbine A-1 Will Be Replaced with Alt-31 |
Iberdrola Renewables, Inc. |
ActingSiteManagerForRugby,DennisKuhns |
11/17/2008 |
3 |
| 108 |
Rugby Wind LLC Weekly Project Information, Week Ending Nov. 16, 2008 |
Rugby Wind LLC |
Dennis Kuhns, Iberdrola Renewables |
11/16/2008 |
2 |
| 107 |
Rugby Wind LLC Weekly Project Information, Week Ending Nov. 8, 2008 |
Rugby Wind LLC |
Dennis Kuhns, Iberdrola Renewables |
11/12/2008 |
2 |
| 106 |
Letter re. Preconstruction Summary - Notice of Construction Start |
Iberdrola Renewables, Inc. |
Tim Seck, Director of Developement |
9/29/2008 |
1 |
| 105 |
Affidavit Certified - Commission Motion Approving Turbine Site Changes and the Re-Caption Cases to Recognize Corporate Name Change |
Public Service Commission |
|
9/16/2008 |
3 |
| 104 |
Staff Memorandum for 8-27-08 Informal Hearing |
Public Service Commission |
Jerry Lein |
8/27/2008 |
1 |
| 103 |
Affidavit Certified - 1st Reissued Certificate of Site Compatibility Number 5 |
Public Service Commission |
|
9/12/2008 |
3 |
| 102 |
Amended Certificate of Authority for Name Change |
Iberdrola Renewables, Inc. |
Fredrikson&ByronPA, Lawrence Bender |
9/10/2008 |
2 |
| 101 |
Motion to Approve Turbine Site Plan Changes |
Public Service Commission |
|
9/10/2008 |
1 |
| 100 |
Layout Comparison Map of Alternate Turbine Locations |
Iberdrola Renewables, Inc. |
Fredrickson&Byron, Lawrence Bender |
9/2/2008 |
2 |
| 99 |
Motion to Reissue Certificate of Site Compatibility and First Reissued Certificate of Site Compatibility No. 5 |
Public Service Commission |
|
8/27/2008 |
2 |
| 98 |
Name Change Letter - Request to Release Certificates |
Iberdrola Renewables, Inc. |
|
8/22/2008 |
1 |
| 97 |
Request for Revised Turbine Site Locations |
Iberdrola Renewables f/k/a PPM Energy Inc. |
Fredrikson&Byron, PA, Lawrence Bender |
8/20/2008 |
1 |
| 96 |
Letter and Layout Comparison Map - Proposed Location of Suzlon Turbines vs. GE Turbines |
Iberdrola Renewables f/k/a PPM Energy, Inc. |
Fredrickson&ByronPA, Lawrence Bender |
8/14/2008 |
2 |
| 95 |
Motion |
Public Service Commission |
|
2/23/2007 |
1 |
| 94 |
Staff refund summary |
Public Service Commission |
|
2/23/2007 |
1 |
| 93 |
Staff memo |
Public Service Commission |
|
2/14/2007 |
1 |
| 92 |
Cover letter explaining interim refund |
Public Service Commission |
G. Geiger |
2/23/2007 |
1 |
| 91 |
Comments |
State Historical Society of North Dakota |
|
3/28/2006 |
1 |
| 90 |
Comments |
State Historical Society of North Dakota |
|
10/27/2005 |
1 |
| 89 |
Affidavits of Service |
Public Service Commission |
|
10/4/2005 |
9 |
| 88 |
Motion approving Order |
Public Service Commission |
Public Service Commission |
10/3/2005 |
1 |
| 87 |
Findings of Fact, Conclusions of Law and Order |
Public Service Commission |
|
10/3/2005 |
13 |
| 86 |
Certificate of Site Compatibility No. 5 |
Public Service Commission |
|
10/3/2005 |
1 |
| 85 |
Affidavit of Publication |
North Dakota Newspaper Association |
|
9/28/2005 |
1 |