nd.gov - The Official Portal for North Dakota State Government
North Dakota: Legendary. Follow the trail of legends
North Dakota State Public Service CommissionNorth Dakota PSC Home Page

North Dakota State Public Service Commission

Quick Links

Navigation

600 E. Boulevard Ave., Dept. 408
Bismarck, ND 58505-0480

701.328.2400 - Phone
877.245.6685 - Toll-Free
800.366.6888 - TTY
701.328.2410 - Fax
ndpsc@nd.gov

Know What's Below, Call before you dig.

Jurisdiction: Abandoned Mine Lands

2010 Completed Projects Archive

2010 Buechler/Velva Project

This project was designed to eliminate about 10,750 feet of dangerous highwalls on a 150 acre site at an abandoned mine southwest of Velva.  Reclamation was to have been achieved by excavating material from spoil piles to backfill the highwalls and pits.  Approximately 1,850,000 cubic yards of excavation were required for this project.  Unfortunately the contractor, Smith Contracting of Butte, MT, ceased work and abandoned this project prior to completion.  The project was completed under a tender agreement with Smith’s bonding company by Kern & Tabery, Inc. of Wadena, MN, September 30, 2011. The total amount paid to both contractors was approximately $1,447,264.80.

2010 Williams County Road 9 Phase 5 Project

The objectives of this project were to drill holes to locate underground mined workings and to pump a cementitious grout through these holes to fill the mine voids and reduce the likelihood of collapse. This was the fifth and possibly last year of a multi-year project in areas along Williams County Road 9 and other nearby residential areas east of Williston. Approximately 25,833 feet were drilled and 1290 cubic yards of grout were pumped into underground mine voids at this project site. The contractor for this project was B & C Concrete Pumping, Inc, of Williston, ND.  Work was completed November 18, 2010, at a final cost of $230,793. A separate contract was issued to Material Testing Services, LLC, of Minot, for testing of the grout used for this project and the final cost was $12,516.

2010 Beulah/Zap Phase 11 Project

The objectives of this project were to drill holes to locate underground mined workings and to pump a cementitious grout through these holes to fill the mine voids and reduce the likelihood of collapse. This was the eleventh year of a multi-year project near Beulah and Zap. Approximately 15,000 feet were drilled and 6870 cubic yards of grout were pumped into underground mine voids at this project site. The contractor for this project was B & C Concrete Pumping, Inc, of Williston, ND.  Work was completed November 15, 2010, at a final cost of $669,021.40. A separate contract was issued to Geoserv, Inc, of Bismarck, for testing of the grout used for this project and the final cost was $27,335.

2010 Beulah KDKT Emergency Project

This project was conducted to repair a large and dangerous sinkhole caused by underground mine collapse near the KDKT Radio Tower in Beulah.  The sinkhole was partially filled with cementitious grout, which was allowed to harden, and then topped off with dirt. The contractor for this project was Basaraba Excavating of Wilton, and the final cost was $24,000.  Work was completed June 28, 2010.

2010 Coal Fire Suppression Project

This project was conducted to extinguish four coal outcrop fires in Slope County, located within the U.S. Forest Service's Little Missouri National Grasslands and on nearby privately owned property.  The contractor for this project was Dave Titus Excavating of Bismarck, and the final cost was $20,975.  Work was completed October 23, 2010.

2010 Buechler/Velva Maintenance

This project was conducted to repair erosion and stabilize a waterway at the Buechler/Velva Site. The contractor for this project was Dig It Up Backhoe Service of Minot, and the final cost was $15,882.09.  Work was completed November 9, 2010.

 

Legal Links

Accessibility Links