nd.gov - The Official Portal for North Dakota State Government
North Dakota: Legendary. Follow the trail of legends
North Dakota State Public Service CommissionNorth Dakota PSC Home Page

North Dakota State Public Service Commission

Quick Links

Navigation

600 E. Boulevard Ave., Dept. 408
Bismarck, ND 58505-0480

701.328.2400 - Phone
877.245.6685 - Toll-Free
800.366.6888 - TTY
701.328.2410 - Fax
ndpsc@nd.gov

Know What's Below, Call before you dig.

Jurisdiction: Abandoned Mine Lands

1998 Completed Projects Archive

Beulah/Zap Phase II AML Project Summary

Project Type: Underground, pressurized grout remote backfilling
AML Priority: #14
Note: Due to financial limitations work was only done in 1998 at one of the Beulah Sites
Location: SW¼,SW¼,SW¼ of Section 12, T144N, R88W, Mercer County, at the junction of US Highway 200 and ND Highway 49 (Black Diamond Lounge Site)
Acreage: Less than 10 acres
Project Dates: July 27-September 2, 1998
Contractors: Thiem Drilling, Incorporated of Williston (Construction) and Geoserv Inc., of Bismarck (Material Testing)
Bid Volume: 4750 cubic yards grout
Actual Volume: 6205 cubic yards grout
Bid Price: $269,687.50 (Thiem) and $14,065.00 (Geoserv)
Actual Price: $311,811.50 (Thiem) and $12,202.00 (Geoserv)

This project phase was conducted to complete reclamation work begun in 1997 near a building complex located approximately one mile north of Beulah. This building complex presently includes the Ragtop Maltshop and Café, the Black Diamond Lounge, and the Hook Line and Sinker bait shop and convenience store. The reclamation technique utilized was Pressurized Grout Remote Backfilling. In this technique, a cementitious grout is pumped under pressure through drilled holes into the mine cavities to fill them and reduce the likelihood of collapse.

In 1997, grout was pumped to stabilize collapsing mined workings directly beneath the Black Diamond Lounge, near the Hook Line and Sinker, and beneath portions of the driveway and parking lot. In 1998, grout was pumped into collapsing mined workings beneath the remainder of the driveway, beneath several occupied mobile homes, and beneath the east ditch of Mercer County Road 21. This project phase marks the completion of a large reclamation project. In 1997 and 1998, over 35,000 feet of rotary drilling was conducted and nearly 13,000 cubic yards (approximately 25,000 tons) of grout were pumped to fill collapsing mine workings at this site. In addition, approximately 41,000 tons of slurry was injected at this site during a project conducted in 1983. The total combined costs of the 1983, 1997 and 1998 grouting projects at this site exceed $1.2 million.

Mining History

Background of Reclamation Project

Custer Phase II

The North Dakota Public Service Commission reclaimed the Phase 2 portion of this abandoned surface coal mine site. This phase of the project involved the backfilling the central portion of the west highwall. Approximately 287,000 cubic yards of spoil was excavated from the adjacent spoil piles to backfill the highwall. After completion of the dirt work operations the site was fertilized, seeded and mulched. The construction cost for the Phase 2 Project was $161,322.69. The Custer Phase 2 Project started on June 16, 1998 and was completed on October 10, 1998. The following are pictures that illustrate pre- and post-mining conditions:

Graf

The North Dakota Public Service Commission reclaimed potentially hazardous portions of the Graf abandoned surface coal mine site. This project involved the backsloping of the west highwall. Approximately 56,000 cubic yards of spoil was excavated. The excavated material was used to backfill the north and south highwalls. After completion of the dirt work operations the site was fertilized, seeded and mulched. The construction cost for the Graf Project was $48,380.00. Reclamation began May 11, 1998 and was completed on June 30, 1998. The following is a:

Legal Links

Accessibility Links