nd.gov - The Official Portal for North Dakota State Government
North Dakota: Legendary. Follow the trail of legends
North Dakota State Public Service CommissionNorth Dakota PSC Home Page

North Dakota State Public Service Commission

Quick Links

Navigation

600 E. Boulevard Ave., Dept. 408
Bismarck, ND 58505-0480

701.328.2400 - Phone
877.245.6685 - Toll-Free
800.366.6888 - TTY
701.328.2410 - Fax
ndpsc@nd.gov

Know What's Below, Call before you dig.

Jurisdiction: Abandoned Mine Lands

2013 Completed Projects Archive

2013 Havelock C Project

This project involved the backfilling of about 2000 feet of highwalls and mine pits at a 16 acre abandoned surface mine in Hettinger County southeast of New England. Approximately 198,000 cubic yards of excavation was required for this project. The contractor was Martin Construction, Inc. of Gladstone, ND. Work was completed July 30, 2012, and the contract cost was $246,620.

2013 Richter Project

This project involved the backfilling of about 2000 feet of highwalls and mine pits at a 40 acre abandoned surface mine in Morton County northeast of Glen Ullin. Approximately 130,000 cubic yards of excavation was required for this project. The contractor was Baranko Brothers, Inc. of Dickinson, ND. Work was completed August 13, 2012, and the contract cost was $261,682.50.

2013 Beulah/Zap Phase 14 Project

The objectives of this project were to drill holes to locate underground mined workings and to pump a cementitious grout through these holes to fill the mine voids and reduce the likelihood of collapse. Approximately 6,106 feet were drilled and 7,119 cubic yards of grout were pumped into underground mine voids at this project site. The contractor for this project was B & C Concrete Pumping, Inc. of Williston, ND. Work was completed September 10, 2013, and the contract cost was $951,844.77. A separate contract was issued to Northeast Technical Services, Inc. for testing of the grout used for this project and the final cost was $36,240.

2013 Scranton/Bowman Project

The objectives of this project were to drill holes to locate underground mined workings and to pump a cementitious grout through these holes to fill the mine voids and reduce the likelihood of collapse. Approximately 15,590 feet were drilled, four monitoring wells were installed and 3,498 cubic yards of grout were pumped into underground mine voids at this project site. The contractor for this project was B & C Concrete Pumping, Inc. of Williston, ND. Work was completed January 1, 2014, and the contract cost was $858,092.14. A separate contract was issued to Northeast Technical Services, Inc. for testing of the grout used for this project and the final cost was $28,646. A separate contract was also issued to Water Supply, Inc. of Mandan, ND, for groundwater monitoring and hydrogeological consulting. This contract is ongoing.

2013 Sinkhole Filling Project

This project was conducted to fill approximately 180 dangerous sinkholes resulting from collapse of underground coal mines. Sinkholes were filled near the cities of Beulah, Zap, Richardton, Dickinson, Williston, Hanks, Noonan, Velva, Washburn, Wilton, Haynes and Scranton, North Dakota. Repairs were also made to erosion features on a reclaimed surface mine near Velva, ND. The contractor for this work was Pleasant and Sons Construction of Greenville, KY. Work was completed November 10, 2013, and the 2013 contract cost was $128,709.

 

Legal Links

Accessibility Links